Tire

Türkiye · 2025–

80,000 t/year

253,230㎡ · 8 Pyrolysis + 4 rCB sets

Active + rCB Refinery

Gangjin owns the overall process design and supplies the main equipment package outside the reactors, coordinating engineering with the civil contractor on site. The scope continues through commissioning and operational handover.

Türkiye · 2022–2025

80,000 t/year

8 Pyrolysis + 5 rCB sets

Completed + rCB Refinery

Ukraine · 2026–

40,000 t/year

4 Pyrolysis + 2 rCB sets

Active + rCB Refinery

EU · 2024

6,000 t/year

1 Pyrolysis set

Completed

Europe · 2026

Pyrolysis package

Multi-contractor EPC

Pipeline